6.2Recurring issues (playbook)
The essentials in 30 seconds
- Diagnose: a symptom = likely causes = a sequence of actions — you do not fix a schedule at random.
- Fundamentals first: check the basics (automatic mode, calendar, links) before going further, one correction at a time.
- Root cause: a symptom that keeps coming back is not eight incidents, it is a missing fundamental (mode, links, calendar, baseline, tracking) to be fixed at the root.
Meriem's thread — the table taped next to her screen
Meriem keeps this playbook displayed near her screen in Algiers. Verdict after a quarter: three lines served her most — “the schedule does not recalculate”, “red resources” and “impossible to track variances”. For each, she ended up applying the sequence (symptom, causes, actions) instead of trying random fixes.
Observed symptom, verified causes, actions in order: the reflex comes in three steps.
One reflex per symptom
Most blockers in Project are classics. Linking each symptom to its likely causes and to a sequence of actions saves precious time and brings you back to the fundamentals of a healthy schedule.
Fundamentals first
You first check the basics (automatic mode? right calendar? links rather than dates?) before looking further. One correction at a time, otherwise you no longer know what fixed the problem.
Treat the root cause
The same symptom coming back is not ten incidents: it is a missing fundamental (automatic mode, link rather than date, right calendar, baseline, up-to-date tracking) to be fixed at the root.
| Symptom | Likely causes | Actions |
|---|---|---|
| The schedule does not recalculate when I change a duration | tasks in manual mode | switch to automatic scheduling; set the default mode to auto (N1.2) |
| A 5-day task ends too late | wrong calendar (weekends/public holidays) | check “Change Working Time”: time off, hours (N0.4) |
| The schedule does not move when an upstream task slips | dates entered by hand instead of links | link tasks through dependencies; remove rigid constraints (N1.3, N1.4) |
| The duration becomes absurd after an assignment | task type unsuitable for the intent | choose which variable to fix (units/duration/work) before changing (N2.3) |
| Red (overallocated) resources | overlap or assignment beyond capacity | audit/level within available slack, shift or reassign (N3.2) |
| Impossible to track variances / empty EVM | no baseline, or work/costs not entered | set a baseline before starting, keep progress up to date, set the status date (N3.3, N4.3) |
Script ready to say — diagnosing a schedule (30 s)
“My symptom: [the schedule does not recalculate / costs at zero / red resources]. I check the likely cause from the playbook (mode, calendar, links, task type, overallocation, baseline) and apply the targeted action.”
The reflex comes in three steps: symptom, cause, action.
Script ready to say — going back to fundamentals (30 s)
“Am I linking rather than dating? Am I in automatic mode? Is my calendar right? Have I set a baseline? If any answer is no, I fix the base before going further.”
Always check the fundamental before the detail.
Copy-paste template — schedule diagnosis
Does not recalculate -- manual mode? -> switch to auto
Task ends too late -- calendar? -> working time, time off
Does not move -- hard dates? -> link through dependencies
Absurd duration -- task type? -> choose the variable to fix
Red resources -- overallocation?-> audit / level
Empty EVM -- baseline? -> save the baseline
Copy-paste template — schedule incident sheet
Symptom : [what I see in Project]
Cause : [verified, not assumed]
Action : [one correction at a time]
Proof : [what I retested]
Root? : [isolated symptom or missing fundamental]
VSE / small budget
No formal table: a symptom, the likely cause, the action and the proof, noted on a sheet near the schedule.
Algiers SME
Build local realities into the diagnosis: irregular supplies, bad weather, several projects at once, French content.
Remote / hybrid
Add a screenshot to the diagnosis: at a distance, a written symptom and proof avoid back-and-forth.
Intercultural
Make findings explicit in writing: what seems obvious (which field, which format) is not obvious to everyone.
48h challenge — apply it tomorrow
Identify 1 current symptom in your schedule (does not recalculate, red resources, costs at zero, empty EVM), apply the playbook line (named symptom + verified cause + targeted action) and prove it.
- I can link a schedule symptom to its likely causes.
- I check the fundamental before the detail, one correction at a time.
- I distinguish an isolated symptom from a missing fundamental.
Meriem changes a duration but the schedule does not move. Which playbook reflex applies?
Reflex: name the symptom, verify the cause, apply the targeted action — and spot the missing fundamental behind a recurring symptom.