4.3 · Earned value (EVM) in Project

Level 4 · Expert: analysis, customization & reporting

4.3Earned value (EVM) in Project

Goal: Measure cost/schedule performance objectively (CV, SV, CPI, SPI) and anticipate the final cost, beyond % complete.
Estimated time: 16 min · self-paced reading · If you only have 5 min: read “The essentials in 30s” + the diagram.

The essentials in 30 seconds

  • Earned value (EVM) measures performance in costs AND schedule from three values: PV (planned work), EV (work accomplished) and AC (cost actually spent).
  • From this follow the variances CV = EV − AC and SV = EV − PV, and the indices CPI = EV/AC and SPI = EV/PV; an index below 1 signals a drift (cost or schedule).
  • EVM is a quantified, anticipatory diagnosis: it projects the cost at completion (EAC) and lets you act before the end — far beyond a simple “% complete”.

Running mini-case — Meriem diagnoses her project mid-way

Meriem, project manager in an engineering & construction (BTP) company in Algiers, must reassure her management mid-way through the extension project. “% complete” says nothing about real health: she therefore activates earned value. She first checks the prerequisites — a saved baseline and up-to-date progress tracking, with a correct status date. She displays the Earned Value table and reads: planned value (PV), earned value (EV) and actual cost (AC), then the CV and SV variances and the CPI and SPI indices. Her CPI stands at 0.9: she is spending more than the value produced. She projects a cost at completion (EAC) and warns management BEFORE the budget explodes — a quantified, anticipatory diagnosis.

Standalone case for this section: it returns in the course, the diagram, the script and the 48h challenge of section 4.3.

1. Three base values

Earned value (EVM) objectively measures a project's performance in costs AND schedule. It rests on three values: planned value (PV), the budgeted cost of the work planned to date; earned value (EV), the budgeted cost of the work actually accomplished; actual cost (AC), what has actually been spent. Project calculates all this provided there is a baseline and up-to-date progress tracking.

2. Variances and indices

From these values follow the cost variance CV = EV − AC and the schedule variance SV = EV − PV, as well as the indices CPI = EV/AC (costs) and SPI = EV/PV (schedule). A CPI below 1 means you are spending more than the value produced; an SPI below 1 means you are progressing slower than planned. A negative variance is unfavorable.

3. Anticipate, not just observe

The real value of EVM is anticipatory: from the CPI, you project the cost at completion (EAC) and act before the end. A CPI of 0.9 mid-way probably announces a final overrun if nothing changes. EVM turns tracking into a quantified diagnosis, far beyond a simple “% complete”.

Common misinterpretation: “% complete is enough to steer a project; EVM indicators are read without any preparation; and a CPI below 1 is a good sign.” No, triple error. % complete alone says nothing about cost/schedule performance: EVM cross-references planned, accomplished and actual. EVM requires prerequisites — a saved baseline, up-to-date tracking, filled-in costs and a correct status date: without them, the indicators are empty or wrong. And a CPI below 1 is unfavorable: you are spending more than the value produced. Meriem therefore checks the prerequisites before interpreting.
Earned value (EVM): costs AND schedule From the three base values follow the variances then the indices, up to the projection of the final cost. PV, EV, AC Planned,earned, actualCV & SV Cost and schedulevariances (− = unfavorable)CPI & SPI Indices(below 1 = drift)
From the three base values follow the variances then the indices, up to the projection of the final cost.
Text version of the diagram (SEO / screen readers / translation): 1) Meriem, project manager in an engineering & construction (BTP) company in Algiers, learns that earned value (EVM) objectively measures performance in costs AND schedule from three values: planned value (PV), earned value (EV) of the work accomplished and actual cost (AC). 2) She remembers that from this follow the variances CV = EV − AC and SV = EV − PV, and the indices CPI = EV/AC and SPI = EV/PV, an index below 1 signaling a drift; EVM is anticipatory and lets you project the cost at completion (EAC). 3) Mid-way, she checks her prerequisites (baseline + tracking + status date), reads a CPI of 0.9 and warns management of a likely overrun. Lesson: % complete alone is not enough; EVM offers a quantified diagnosis to act before the end.

🔎 Concrete example — 🔎 Concrete example — Anticipating the overrun

A diagnosis well before the end, as Meriem does:

CPI = 0.9 mid-way -> 0.90 EUR of value per euro spent.
If nothing changes, final overrun likely.
-> project a cost at completion (EAC) and act BEFORE.

Reading: a CPI below 1 is not an accounting detail: it announces a final overrun if nothing changes.

Lesson: you project the cost at completion (EAC) and act early, instead of observing after the fact.

Section vocabulary

Planned value (PV)
Budgeted cost of the work planned at a given date (from the baseline).

Simple example: Meriem reads the PV at her status date.

What it is not: the cost actually spent to date.

Reflex: planned work → the PV.

Earned value (EV)
Budgeted cost of the work actually accomplished to date (progress × budget).

Simple example: Meriem measures the EV of completed work.

What it is not: the work only planned, not yet done.

Reflex: work accomplished → the EV.

Actual cost (AC)
Cost actually spent for the work accomplished to date.

Simple example: Meriem adds up the invoices committed to date.

What it is not: the amount budgeted but not yet spent.

Reflex: what has gone out → the AC.

CPI / SPI
Performance indices: CPI = EV/AC (costs), SPI = EV/PV (schedule); below 1 = drift.

Simple example: Meriem's CPI is 0.9: cost drift.

What it is not: a simple overall progress percentage.

Reflex: cost/schedule efficiency → CPI/SPI.

Variances CV / SV
CV = EV − AC (cost variance); SV = EV − PV (schedule variance); negative = unfavorable.

Simple example: Meriem notes a negative CV on a phase.

What it is not: an index (ratio), not a difference.

Reflex: planned/actual difference → CV or SV.

In practice — In practice — Use earned value

  1. Make sure you have a saved baseline (level 3) and up-to-date progress tracking: EVM prerequisites, as Meriem checks.
  2. Display an earned value table (View > Tables > More Tables > Earned Value / Cost indicators).
  3. Read PV, EV and AC, then the CV and SV variances and the CPI and SPI indices.
  4. Interpret: CPI below 1 = overrun, SPI below 1 = delay; project the cost at completion (EAC).
You measure cost/schedule performance objectively (CV, SV, CPI, SPI) and anticipate the final cost: a quantified diagnosis well beyond % complete.

Step-by-step script — read EVM like Meriem (5 min)

1) Check the prerequisites: a saved baseline, up-to-date progress tracking and a correct status date. 2) Display the Earned Value table (View > Tables > More Tables). 3) Note PV, EV and AC. 4) Calculate or read the variances CV = EV − AC and SV = EV − PV, then the indices CPI = EV/AC and SPI = EV/PV. 5) Interpret with the marker “1 = on plan” and project the cost at completion (EAC).

Without a baseline or up-to-date tracking, the indicators remain empty: it is the number one prerequisite of earned value.

Copy-paste template — my EVM reading

Values  : PV (planned) | EV (earned) | AC (actual)
Variances: CV = EV - AC (cost)  | SV = EV - PV (schedule)
Indices : CPI = EV / AC       | SPI = EV / PV
Marker  : 1 = on plan; < 1 = drift (cost or schedule)
Prerequisites: baseline + up-to-date tracking + status date
Anticipate: project the cost at completion (EAC)

An overrun detected

Meriem reads a CPI of 0.9 mid-way and alerts management.

A measured delay

An SPI below 1 shows that work is progressing slower than planned.

Prerequisites checked

Meriem checks her baseline and status date before interpreting.

Projected final cost

Meriem projects a cost at completion (EAC) to anticipate.

Caution: Generic reminder: earned value indicators rely on data you enter (baseline, progress, costs): they are only worth something if that data is reliable and up to date. Before communicating a CPI/SPI or a cost at completion, cross-check them with the field and with the finance department's figures, present them as estimates rather than accounting, and respect the confidentiality of project amounts.

✓ Best practices

  • Check the prerequisites: baseline + tracking + status date.
  • Read variances (CV, SV) and indices (CPI, SPI) together.
  • Use the indices to anticipate and act early.

✗ Common pitfalls

  • Expecting EVM figures without a baseline (impossible).
  • Forgetting to fill in costs (EV/AC null).
  • Neglecting the status date (surprising values).

Key takeaways

  • EVM cross-references three values: planned value (PV), earned value (EV), actual cost (AC).
  • Variances: CV = EV − AC (cost), SV = EV − PV (schedule); negative = unfavorable.
  • Indices: CPI = EV/AC, SPI = EV/PV; below 1 = drift.
  • Prerequisites: a saved baseline AND up-to-date progress tracking.

48h challenge — apply it tomorrow

Like Meriem, display your project's Earned Value table and note PV, EV and AC, then the CV/SV variances and the CPI/SPI indices. Write in one sentence the diagnosis (cost or schedule drift?), then project a cost at completion (EAC). If the indicators are empty, check the baseline and the status date before concluding.

Section exit checklist
  • I know what PV, EV and AC measure and where they come from.
  • I interpret CV, SV, CPI and SPI with the marker “1 = on plan”.
  • I check the prerequisites and project a cost at completion.
Self-assessment 1-5: do I interpret a CPI/SPI without hesitation?Self-assessment 1-5: do I know why a baseline is necessary for EVM?

Frequently asked questions

Why are my earned value indicators empty or wrong?

EVM requires two often missing prerequisites: a saved baseline (without a baseline, no PV, therefore no calculation) and up-to-date progress tracking with costs filled in (otherwise EV and AC are null or inconsistent). Also check the project's status date (Project > Project Information): EVM is calculated at that date. Baseline + costs + progress + correct status date, and everything calculates automatically.

How to interpret CPI and SPI simply?

Remember “1 = right on plan, less than 1 = bad, more than 1 = good”. The CPI (costs): at 0.9, you get 0.90 € of value per euro spent, so you are overrunning; at 1.1, you are more efficient than planned. The SPI (schedule): at 0.8, you have completed only 80 % of the work planned to date, so you are late. The main point is to anticipate: a CPI of 0.9 mid-way announces a likely final overrun if nothing changes.

Check your understanding

What does earned value (EVM) measure?