12 questions to validate level 4 with Meriem, project manager in an engineering & construction (BTP) company in Algiers: tables and analysis views, custom fields and indicators, earned value (EVM), reports and dashboards, timeline and sharing.
Answer everything, then click Check: your score and explanations will appear.
4 · Recall
1. What do groups do in a Project schedule?
A group hides nothing: it arranges rows by category with subtotals, whereas the filter reduces what you see.
4 · Application
2. Meriem wants “all late tasks, by owner, by size”. What does she combine?
Filtering “late tasks”, grouping “by owner” then sorting by size produce the targeted analysis view.
4 · Arbitration
3. Meriem's display looks “broken”: tasks have disappeared. What does she check first?
An incomplete display very often comes from a filter left active: you clear it (No Filter) before concluding there is a bug.
4 · Recall
4. What is a custom field in Project?
Custom fields (Text, Number, Cost, Flag…) can be renamed and calculated by a formula from other fields.
4 · Application
5. Meriem wants an eye to spot cost overruns at once. What does she create?
A graphical indicator displays a green/orange/red dot according to a field's value: the eye goes straight to tasks at risk.
4 · Recall
6. What do PV, EV and AC represent in earned value?
PV = planned value, EV = earned value (work accomplished), AC = actual cost: the three values at the root of EVM.
4 · Application
7. Meriem's CPI is 0.9 mid-way. How does she interpret it?
CPI = EV/AC below 1: you spend more than the value produced; a 0.9 mid-way announces a final overrun if nothing changes.
4 · Arbitration
8. Meriem's EVM indicators are empty. Which prerequisite is most often missing?
Without a saved baseline or up-to-date progress tracking, there is no PV or EV/AC: baseline and tracking are the prerequisites of EVM.
4 · Recall
9. What do you find in Project's Report tab?
The Report tab offers dynamic pages mixing charts, tables and indicators, updated in real time.
4 · Arbitration
10. Meriem hesitates between keeping reporting in Project or exporting to Excel. What does she retain?
Built-in reports stay up to date and are enough for routine reporting; you export to Excel (pivot tables) or Visio for tailor-made work.
4 · Recall
11. What is the Timeline in Project?
The Timeline is the “one-page” summary time line (phases, milestones, major tasks), ideal for communicating to management.
4 · Application
12. Meriem wants to share the schedule with a partner who does not have Project. What does she do?
PDF export is universal; the Timeline copies into PowerPoint for a presentation. Avoid sending the raw .mpp without Project.
What's next?
Score ≥ 80 %: move on to Level 5 — multi-project, collaboration & automation with Meriem.
Score between 50 % and 80 %: review the section(s) you missed (4.1 tables/filters, 4.2 custom fields, 4.3 earned value, 4.4 reports, 4.5 timeline), reread the course, then retake the test.
Score < 50 %: reread the whole level 4 while applying each 48h challenge (build an analysis view, light up traffic lights, read earned value, produce reporting, adapt the timeline) before trying again.
And after? Keep your analysis views, your indicators, your EVM reading, your reports and your timeline: level 5 puts them to work for multi-project, collaboration and automation.