Level 4 exam — harder

Exam — fresh questions

4 · Recall

1. What do groups do in a Project schedule?

A group hides nothing: it arranges rows by category with subtotals, whereas the filter reduces what you see.
4 · Application

2. Meriem wants “all late tasks, by owner, by size”. What does she combine?

Filtering “late tasks”, grouping “by owner” then sorting by size produce the targeted analysis view.
4 · Arbitration

3. Meriem's display looks “broken”: tasks have disappeared. What does she check first?

An incomplete display very often comes from a filter left active: you clear it (No Filter) before concluding there is a bug.
4 · Recall

4. What is a custom field in Project?

Custom fields (Text, Number, Cost, Flag…) can be renamed and calculated by a formula from other fields.
4 · Application

5. Meriem wants an eye to spot cost overruns at once. What does she create?

A graphical indicator displays a green/orange/red dot according to a field's value: the eye goes straight to tasks at risk.
4 · Recall

6. What do PV, EV and AC represent in earned value?

PV = planned value, EV = earned value (work accomplished), AC = actual cost: the three values at the root of EVM.
4 · Application

7. Meriem's CPI is 0.9 mid-way. How does she interpret it?

CPI = EV/AC below 1: you spend more than the value produced; a 0.9 mid-way announces a final overrun if nothing changes.
4 · Arbitration

8. Meriem's EVM indicators are empty. Which prerequisite is most often missing?

Without a saved baseline or up-to-date progress tracking, there is no PV or EV/AC: baseline and tracking are the prerequisites of EVM.
4 · Recall

9. What do you find in Project's Report tab?

The Report tab offers dynamic pages mixing charts, tables and indicators, updated in real time.
4 · Arbitration

10. Meriem hesitates between keeping reporting in Project or exporting to Excel. What does she retain?

Built-in reports stay up to date and are enough for routine reporting; you export to Excel (pivot tables) or Visio for tailor-made work.
4 · Recall

11. What is the Timeline in Project?

The Timeline is the “one-page” summary time line (phases, milestones, major tasks), ideal for communicating to management.
4 · Application

12. Meriem wants to share the schedule with a partner who does not have Project. What does she do?

PDF export is universal; the Timeline copies into PowerPoint for a presentation. Avoid sending the raw .mpp without Project.