2.3 · Task Types & Effort-Driven Scheduling

Level 2 · Intermediate: Resources, Assignments & Costs

2.3Task Types & Effort-Driven Scheduling

Goal: Control how Project recalculates each task (type + effort-driven scheduling) for realistic durations and workloads.
Estimated time: 14 min · self-paced reading · If you only have 5 min: read “The essentials in 30s” + the diagram.

The essentials in 30 seconds

  • The task type decides which variable stays fixed in the triangle: Fixed Units (default, units do not move), Fixed Duration (the deadline does not move), Fixed Work (total effort is constant).
  • Effort-driven scheduling redistributes a constant total work: adding resources reduces duration without changing effort.
  • Consciously choosing the type per task means controlling your schedule instead of suffering it: known effort → Fixed Work; imposed deadline → Fixed Duration.

Running mini-case — Meriem masters task recalculation

Meriem, project manager at an engineering & construction (BTP) company in Algiers, finds that a duration exploded after an assignment. Rather than fixing it at random, she opens the task details (double-click > Advanced) and sets the type. On 'Writing the technical file', the effort is known (40 h, whoever does it): she chooses Fixed Work and enables effort-driven scheduling, so adding an engineer reduces the duration without inflating the effort. On 'Client training', the duration is imposed (3 days): she switches the task to Fixed Duration. She also spots the 'Effort driven' checkbox and remembers that a bad setting produces absurd durations. From now on, she asks herself which variable to fix BEFORE making a change.

Standalone case for this section: it comes back in the lesson, the diagram, the script and the 48h challenge of section 2.3.

1. Which variable stays fixed

Each task has a type that decides which variable stays fixed in the Work/Duration/Units triangle. Fixed Units (default): units do not move; changing work changes duration. Fixed Duration: duration does not move; changing work changes units. Fixed Work: total effort is constant; adding resources reduces duration.

2. Effort-driven scheduling

On top of that comes effort-driven scheduling (effort-driven): when enabled, adding or removing resources redistributes a constant total work (more hands = less time), without changing the effort.

3. Control instead of suffer

A bad setting produces absurd durations or workloads. Meriem asks herself 'which variable do I want to fix' before changing anything, then sets the type: known effort → Fixed Work (often with effort-driven scheduling); imposed deadline → Fixed Duration. That is the mark of a user who controls their schedule.

Common misinterpretation: 'The default task type always fits; effort-driven scheduling and task type are the same thing; and an absurd duration after assignment is a bug'. No, three mistakes. The default type (Fixed Units) does not fit everything: on a known effort, Fixed Work is better. Effort-driven scheduling is a checkbox (effort-driven) separate from the type (units/duration/work). And a duration that explodes reflects a badly chosen type, not a bug: Project mechanically applies Work = Duration × Units. So Meriem chooses consciously, task by task.
Task types: which variable to fix Fixed Units (default), Fixed Duration or Fixed Work: the type decides what stays constant during recalculation. Fixed UnitsConstant units (default)+Fixed DurationThe deadline does not move+Fixed WorkConstant effort, adjusted duration Effort-driven: + resources = - time (constant work).
Fixed Units (default), Fixed Duration or Fixed Work: the type decides what stays constant during recalculation.
Text version of the diagram (SEO / screen readers / translation): 1) Meriem, project manager at an engineering & construction (BTP) company in Algiers, learns that each task has a type that decides which variable stays fixed: Fixed Units (default, constant units), Fixed Duration (the deadline does not move) or Fixed Work (total effort is constant). 2) She notes that on top of this comes effort-driven scheduling (effort-driven), which redistributes a constant total work: adding resources reduces duration. 3) For 'Writing the technical file' (known effort), she chooses Fixed Work with effort-driven scheduling; for 'Client training' (imposed duration of 3 days), she switches to Fixed Duration. Lesson: consciously choose the type per task, because a bad setting produces absurd durations or workloads.

🔎 Concrete example — 🔎 Concrete example — Choosing consciously

Depending on reality, Meriem decides which variable to fix.

Known effort ('40 h whoever does it')  -> Fixed Work.
Imposed deadline ('3-day training')    -> Fixed Duration.
-> the default (Fixed Units) = thinking in 'someone at X %'.

Reading   : the type decides what stays constant
Reflex    : ask which variable to fix BEFORE changing

Reading: a known effort calls for Fixed Work; an imposed deadline calls for Fixed Duration; the default Fixed Units fits when you think in 'someone at X%'.

Lesson: choosing the type according to reality gives credible durations and workloads, without surprises.

Section vocabulary

Task type
Setting that defines which variable (units, duration or work) stays fixed during a recalculation.

Simple example: Meriem sets 'Writing the file' to Fixed Work.

What it is not: the bar colour in the Gantt chart.

Reflex: which variable to fix → the task type.

Fixed Units
Default type: units stay constant; changing work changes duration.

Simple example: Meriem thinks 'someone at 50%' on a task in Fixed Units.

What it is not: a type where duration stays constant.

Reflex: thinking in % of resource → Fixed Units.

Fixed Duration
Type where duration stays constant; changing work adjusts units (and vice versa).

Simple example: Meriem sets 'Client training' to the imposed 3 days.

What it is not: a task whose total effort never moves.

Reflex: imposed deadline → Fixed Duration.

Fixed Work
Type where total effort stays constant; adding resources reduces duration.

Simple example: Meriem sets 'Writing the file' to Fixed Work (40 h).

What it is not: a task whose units never change.

Reflex: known effort → Fixed Work.

Effort-driven scheduling
Behaviour (effort-driven) where adding or removing resources redistributes a constant total work.

Simple example: Meriem enables effort-driven scheduling and adds an engineer: duration drops.

What it is not: the task type itself, which is a separate setting.

Reflex: more hands = less time → effort-driven scheduling.

In practice — In practice — Mastering task types and effort-driven scheduling

  1. Open a task's details (double-click > Advanced) and locate the 'Type' field and the 'Effort driven' checkbox, like Meriem.
  2. Test 'Fixed Work' + effort-driven scheduling: add a resource and check that duration decreases (constant work).
  3. Test 'Fixed Duration': add a resource and see that duration stays, but work or units change.
  4. For each task, choose which variable to fix according to reality (imposed deadline → fixed duration; known effort → fixed work).
You control how Project recalculates each task (type + effort-driven scheduling): realistic durations and workloads, without surprises.

Step-by-step script — setting the type like Meriem (5 min)

1) Double-click 'Writing the technical file' > Advanced tab. 2) Set the 'Type' field to Fixed Work and tick 'Effort driven'. 3) Add a second engineer: check that duration decreases at constant effort. 4) Switch 'Client training' to Fixed Duration and add a resource: duration stays. 5) For each task, ask yourself which variable to fix BEFORE changing anything.

Effort-driven scheduling is a behaviour; task type is a setting: the two combine, do not confuse them.

Copy-paste template — my type choice per task

Task                         Reality            Type
Writing technical file       effort 40 h        Fixed Work (+ effort-driven)
Client training              imposed 3-day deadline   Fixed Duration
Site monitoring              someone at 50%     Fixed Units (default)
Rule: which variable to fix? decide BEFORE changing

Known effort

Meriem sets 'Writing the file' to Fixed Work: adding an engineer reduces duration, the effort stays at 40 h.

Imposed deadline

Meriem switches 'Client training' to Fixed Duration: duration stays at 3 days whatever happens to work.

Thinking in percentages

On a task in Fixed Units (default), Meriem thinks 'Karim at 50%': the units stay constant.

Effort-driven scheduling

Meriem ticks the 'Effort driven' checkbox: adding resources redistributes a constant total work.

✓ Best practices

  • Ask yourself which variable to fix before changing anything.
  • Known effort → Fixed Work; imposed deadline → Fixed Duration.
  • Use the Smart Tag that appears after a change to choose the recalculation.

✗ Common pitfalls

  • Suffering the default type without thinking.
  • Getting absurd durations after an assignment.
  • Confusing effort-driven scheduling with task type.

Key takeaways

  • The type decides which variable stays fixed: Fixed Units (default), Fixed Duration, Fixed Work.
  • Work = Duration × Units: changing one variable recalculates another according to the type.
  • Effort-driven scheduling redistributes constant work when resources are added or removed.
  • Choosing the right type per task = controlling your schedule instead of suffering it.

48h challenge — apply it tomorrow

Like Meriem, take a task with a known effort (e.g. 40 h) and set it to Fixed Work with effort-driven scheduling: add a resource and note the drop in duration. Then take a task with an imposed duration and set it to Fixed Duration: add a resource and see that the duration does not move. Conclude in one sentence on the value of choosing the type consciously.

Section exit checklist
  • I know which task type to choose depending on what I want to fix.
  • I understand effort-driven scheduling and how it differs from the type.
  • I move from absurd durations to realistic durations and workloads.
Self-assessment 1-5: do I choose the type according to reality?Self-assessment 1-5: can I distinguish task type from effort-driven scheduling?

Frequently asked questions

Which task type should I choose by default?

It depends on what you want to fix: known effort ('40 h, whoever does it') → Fixed Work (often with effort-driven scheduling); imposed duration ('the training lasts 3 days') → Fixed Duration; the default Fixed Units fits when you think in 'someone at X%'.

Why does my duration become absurd when I change an assignment?

The task type does not match your intention: Project mechanically applies Work = Duration × Units. Before changing anything, ask yourself which variable must stay constant and set the type accordingly; the Smart Tag also helps you choose.

Check your understanding

What does the 'task type' decide in Project?

Additional resources (optional, to go further)