2.1 · Creating Resources (Work, Material, Cost)

Level 2 · Intermediate: Resources, Assignments & Costs

2.1Creating Resources (Work, Material, Cost)

Goal: Build a complete resource table (types, rates, capacities): the foundation for assigning, costing and spotting overloads.
Estimated time: 12 min · self-paced reading · If you only have 5 min: read “The essentials in 30s” + the diagram.

The essentials in 30 seconds

  • Project distinguishes three resource types: work (human, consumed in time), material (consumable, in quantity) and cost (one-off expense, an amount).
  • Each resource is entered with a rate, a maximum capacity and a calendar: these are what drive workloads and budget.
  • Maximum capacity (100%, 50%, several units) is used to detect overloads; without it, no workload check is possible.

Running mini-case — Meriem draws up the resource table

Meriem, project manager at an engineering & construction (BTP) company in Algiers, is starting to plan a client project: the extension of an administrative building. The schedule structure is ready; she now needs the 'who' and the 'with what'. She opens the Resource Sheet view and lists: 'Structural engineer' (work resource, rate €400/day, capacity 100%), 'Site team' (work, 300% for three people), 'Concrete' (material, consumed in m³) and 'Crane rental' (cost resource, a one-off amount). She checks that every rate and every maximum capacity is filled in: without them, neither costs nor overloads will be calculated later. This foundation will be used to assign tasks, cost the budget and spot overloads on her teams.

Standalone case for this section: it comes back in the lesson, the diagram, the script and the 48h challenge of section 2.1.

1. Three types of resources

So far we have planned the 'what' and the 'when'; now for the 'who' and the 'with what'. Project distinguishes three resource types: work resources (human — consumed in time), material resources (consumables: concrete, paper, litres — consumed in quantity) and cost resources (one-off expenses: travel, subcontracting — an amount). Meriem lists them in the Resource Sheet view.

2. Rate, capacity, calendar

For each resource, you enter the rate (standard cost, e.g. €400/day), the maximum capacity (100% for full time, 50% for part time, several units for a team) and the availability calendar. These three settings are what will make the calculations correct.

3. The foundation of the schedule

This table is the foundation: it will make it possible to assign resources (2.2), calculate costs (2.4) and detect overloads. A resource with the wrong type or left without a rate costs you later in a false budget and inconsistent workloads.

Common misinterpretation: 'Concrete and crane rental are the same thing; we can leave rates empty to go faster; and maximum capacity is useless as long as we do not go over it'. No, three mistakes. A material resource is counted (m³ of concrete), a cost resource is entered as an amount (a one-off rental): two distinct types. Leaving rates empty freezes costs at zero: without a rate, no budget. And maximum capacity is precisely what reveals overloads as soon as a resource is assigned beyond its availability. So Meriem enters type, rate and capacity from the moment of creation.
The three resource types Work is consumed in time, material in quantity, cost as a one-off amount — all listed in the Resource Sheet. WorkHuman, consumed in time (rate)+MaterialConsumable, in quantity (unit cost)+CostOne-off expense (an amount) Rate + capacity + calendar drive workloads and budget.
Work is consumed in time, material in quantity, cost as a one-off amount — all listed in the Resource Sheet.
Text version of the diagram (SEO / screen readers / translation): 1) Meriem, project manager at an engineering & construction (BTP) company in Algiers, learns that Project distinguishes three resource types: work (human, consumed in time, with a rate), material (consumable measured in quantity, with a unit cost) and cost (one-off expense, a simple amount). 2) She notes that each resource is entered in the Resource Sheet with a rate, a maximum capacity (100%, 50%, several units) and a calendar, and that these settings drive workloads and budget. 3) For her building extension project, she lists 'Structural engineer' at €400/day, 'Site team' at 300%, 'Concrete' per m³ and 'Crane rental' as a one-off amount. Lesson: a complete resource table is the foundation for assigning, costing and spotting overloads.

🔎 Concrete example — 🔎 Concrete example — Material or cost?

Two ways to spend, two types: Meriem classifies her site resources.

'How many units?' (concrete, paper) -> MATERIAL resource.
'How much money?' for a one-off expense -> COST resource.
-> a team = 300% capacity for 3 people.

Reading   : each resource belongs to one precise type
Reflex    : choose a level (person vs team) and stick to it

Reading: material is counted (m³ of concrete), a cost resource is entered as an amount (a one-off rental).

Lesson: a well-typed and well-filled foundation (rate, capacity) is ready for assignment and budget.

Section vocabulary

Work resource
Human resource (person, team) consumed in time; it carries an hourly or daily rate.

Simple example: Meriem creates 'Structural engineer' at €400/day.

What it is not: a batch of concrete, which is consumed in quantity.

Reflex: consumed in time → work resource.

Material resource
Consumable measured in quantity (concrete, paper) with a unit cost, without working time.

Simple example: Meriem adds 'Concrete' per m³ for the building slab.

What it is not: a meeting billed as a lump sum, without quantity.

Reflex: counting units → material resource.

Cost resource
One-off expense assigned to a task (travel, subcontracting): an amount, not a duration.

Simple example: Meriem creates 'Crane rental' as a one-off expense.

What it is not: an engineer whose worked hours are tracked.

Reflex: entering a single amount → cost resource.

Resource Sheet
View listing all project resources with their rates, capacities and calendars.

Simple example: Meriem lists her BTP resources there before planning.

What it is not: the Gantt chart, which shows tasks over time.

Reflex: listing resources → Resource Sheet.

Maximum capacity
Availability of a resource (100% = full time, 200% = two units); the basis for overloads.

Simple example: Meriem sets 300% for the team of three engineers.

What it is not: the duration of a task expressed in days.

Reflex: detecting overloads → maximum capacity.

In practice — In practice — Building the resource list

  1. Open the Resource Sheet view (View > Resource Sheet), like Meriem.
  2. Enter your BTP resources by choosing their type: Work (engineers), Material (concrete), Cost (rental).
  3. Fill in the rates (standard cost) and the maximum capacity (100%, 50%, or several units for a team).
  4. Check the calendar of each work resource (full time, part time) — the basis of availability covered in 2.5.
You have a complete resource table (types, rates, capacities): the foundation for assigning, costing and spotting overloads.

Step-by-step script — drawing up the resource table like Meriem (5 min)

1) Open the Resource Sheet (View > Resource Sheet). 2) Create 'Structural engineer' of type Work, rate €400/day, capacity 100%. 3) Create 'Site team' of type Work, capacity 300% for three people. 4) Create 'Concrete' of type Material, per m³. 5) Create 'Crane rental' of type Cost (a one-off amount). 6) Check rates and capacities: without them, no costs and no overloads.

Keep this table: sections 2.2 (assignment), 2.4 (costs) and 2.5 (availability) build on it.

Copy-paste template — my BTP resource table

Resource Sheet (Meriem)
Work     : Structural engineer   400 EUR/day   100%
Work     : Site team             300% (3 people)
Material : Concrete              unit cost / m3
Cost     : Crane rental          one-off amount
Rule     : type + rate + max capacity + calendar from creation

Resource per person

Meriem creates 'Karim, engineer' as a named work resource, for individual overload tracking.

Resource per trade

In early planning, Meriem uses 'Site team' at 300% for three people, without naming each one.

Site consumable

Meriem tracks concrete in m³ as a material resource: she counts units, not hours.

One-off expense

Meriem models the crane rental as a cost resource, independent of working time.

✓ Best practices

  • Choose the right type: work, material or cost.
  • Enter rate and maximum capacity from the moment of creation.
  • Keep a consistent granularity (one person OR a team, not both in a muddle).

✗ Common pitfalls

  • Forgetting the rates → costs at zero afterwards.
  • Confusing a material resource with a cost resource.
  • Mixing people and teams without any logic.

Key takeaways

  • Three types: work (time), material (quantity), cost (one-off amount).
  • You list them in the Resource Sheet with rate, capacity and calendar.
  • Maximum capacity (100%, 50%, several units) is used to detect overloads.
  • A well-filled table drives workloads and budget.

48h challenge — apply it tomorrow

Like Meriem, open the Resource Sheet and list three resources from your project: one work resource (with rate and maximum capacity), one material resource (per m³ or per unit) and one cost resource (a one-off amount). Write in one sentence why each belongs to its type, then check that rates and maximum capacities are properly filled in.

Section exit checklist
  • I distinguish the three resource types and create them correctly.
  • I enter rate, maximum capacity and calendar.
  • I know where to list resources: the Resource Sheet.
Self-assessment 1-5: do I choose the right resource type without hesitating?Self-assessment 1-5: can I enter rate and maximum capacity from the moment of creation?

Frequently asked questions

What is the difference between a material resource and a cost resource?

A material resource is a quantifiable consumable (concrete in m³, paper in reams): you consume a quantity at a unit cost. A cost resource is a one-off expense with no quantity or time (a ticket, a subcontract): you enter an amount on the task.

A resource per person or per trade/team?

Depends on the granularity you want: per person for close tracking of overloads, per trade/team (e.g. 'Site team' at 300%) for an overall schedule. The important thing is to choose a level and stick to it.

Check your understanding

What are the three resource types in Microsoft Project?

Additional resources (optional, to go further)

Level 2 examFresh, harder questions to test what you've learned