Level 5 exam — harder

Exam — fresh questions

5 · Recall

1. What is a master project used for in Microsoft Project?

The master consolidates subprojects inserted as summary tasks: each file remains autonomous, and inter-project links coordinate dependencies.
5 · Recall

2. What does a shared resource pool help detect in multi-project settings?

The pool consolidates assignments: it reveals that a person requested at 80% on A and 60% on B is overloaded at 140%, which makes arbitration possible.
5 · Recall

3. What is Planner's main limitation compared with Project?

Planner is a light team task tool (Kanban, Teams): no critical path, linked durations, costed resources or budget.
5 · Recall

4. What does a project template (.mpt) capture when you start?

A template (.mpt) is a reusable model project: it lets a similar new project start faster and more accurately, without starting from zero.
5 · Application

5. Meriem inserts an extension schedule into her agency master project. What does this insertion create?

Inserting a subproject creates a link to the original file, not a copy: each .mpp remains openable separately and changes propagate.
5 · Application

6. Meriem sees that a site supervisor is requested at 80% on A and 60% on B in the same week. What does the pool show her?

80% + 60% = 140%: the pool reveals the overload caused by the cumulative total, which requires arbitrating priorities or postponing a site.
5 · Application

7. Daily tracking for a small site team is light. Which tool should be preferred?

For daily “who does what” tracking, Planner (Kanban, Teams) is enough; Project is reserved for expert scheduling.
5 · Application

8. Meriem wants to apply standard formatting to each new project. What does she do first?

The recorder captures the actions performed once and replays them: it is the no-code entry point for automating a repetitive gesture.
5 · Arbitration

9. Meriem has only one dependency between two projects. What does she choose?

For one or two dependencies, a simple inter-project link is enough; the master project is justified for an overview of a set of projects.
5 · Arbitration

10. Three managers each plan on their own and promise the same expert. What is the right reflex?

The pool consolidates assignments: you see the real workload and arbitrate, rather than discovering the overload too late.
5 · Arbitration

11. Before sharing a schedule, which check is most relevant?

The health check verifies that tasks are linked, have few constraints, are baselined and have no floating tasks or forgotten overloads.
5 · Arbitration

12. A colleague wants to automate an action he will perform only once. What does Meriem advise?

You automate what is repetitive: a macro for a single action brings no gain, and it is better to skip it.