12 questions to validate level 5 with Meriem, a project manager at an engineering & construction (BTP) company in Algiers: master project and consolidation, resource pool, Project web/Planner, templates and best practices, VBA automation.
Answer everything, then click Check: your score and explanations will appear.
5 · Recall
1. What is a master project used for in Microsoft Project?
The master consolidates subprojects inserted as summary tasks: each file remains autonomous, and inter-project links coordinate dependencies.
5 · Recall
2. What does a shared resource pool help detect in multi-project settings?
The pool consolidates assignments: it reveals that a person requested at 80% on A and 60% on B is overloaded at 140%, which makes arbitration possible.
5 · Recall
3. What is Planner's main limitation compared with Project?
Planner is a light team task tool (Kanban, Teams): no critical path, linked durations, costed resources or budget.
5 · Recall
4. What does a project template (.mpt) capture when you start?
A template (.mpt) is a reusable model project: it lets a similar new project start faster and more accurately, without starting from zero.
5 · Application
5. Meriem inserts an extension schedule into her agency master project. What does this insertion create?
Inserting a subproject creates a link to the original file, not a copy: each .mpp remains openable separately and changes propagate.
5 · Application
6. Meriem sees that a site supervisor is requested at 80% on A and 60% on B in the same week. What does the pool show her?
80% + 60% = 140%: the pool reveals the overload caused by the cumulative total, which requires arbitrating priorities or postponing a site.
5 · Application
7. Daily tracking for a small site team is light. Which tool should be preferred?
For daily “who does what” tracking, Planner (Kanban, Teams) is enough; Project is reserved for expert scheduling.
5 · Application
8. Meriem wants to apply standard formatting to each new project. What does she do first?
The recorder captures the actions performed once and replays them: it is the no-code entry point for automating a repetitive gesture.
5 · Arbitration
9. Meriem has only one dependency between two projects. What does she choose?
For one or two dependencies, a simple inter-project link is enough; the master project is justified for an overview of a set of projects.
5 · Arbitration
10. Three managers each plan on their own and promise the same expert. What is the right reflex?
The pool consolidates assignments: you see the real workload and arbitrate, rather than discovering the overload too late.
5 · Arbitration
11. Before sharing a schedule, which check is most relevant?
The health check verifies that tasks are linked, have few constraints, are baselined and have no floating tasks or forgotten overloads.
5 · Arbitration
12. A colleague wants to automate an action he will perform only once. What does Meriem advise?
You automate what is repetitive: a macro for a single action brings no gain, and it is better to skip it.
What's next?
Score ≥ 80%: you have mastered multi-project management, collaboration and automation in Project — put these reflexes into practice on Meriem's sites.
Score between 50% and 80%: review the section(s) you missed (5.1 master project, 5.2 resource pool, 5.3 Project web/Planner, 5.4 templates and healthy schedule, 5.5 VBA macros), reread the lesson, then retake the test.
Score < 50%: reread all of level 5 while applying each 48h challenge (consolidate two projects, create a pool and arbitrate, choose the right tool, save a template and check, automate a macro) before trying again.
And afterwards? Keep Meriem's reflexes: consolidate to see the whole, pool to arbitrate workload, choose the right tool, capitalize and automate with discernment — that is what takes you from a single project to managing a portfolio.