12 questions to validate level 3 with Meriem, project manager at an engineering & construction (BTP) company in Algiers: critical path and float, resource overallocation, baseline, progress tracking and rescheduling.
Answer everything, then click Check: your score and explanations will appear.
3 · Recall
1. What is the critical path?
The critical path is the sequence of zero-float tasks that determines the finish date: any delay on it pushes back the project.
3 · Application
2. Meriem wants to absorb a small contingency without moving delivery. Where does she act?
You use the float of non-critical tasks: a delay absorbed in the float does not move the finish date.
3 · Arbitration
3. To shorten a project, what is the right approach?
Only the critical path moves the finish: crashing or fast-tracking, then you recheck that a new critical path does not appear.
3 · Recall
4. What does a resource overallocation correspond to?
An overallocation (overload) occurs when more than the available capacity is demanded: Project flags it in red.
3 · Application
5. Two tasks require the same site supervisor at the same time. What does Meriem do?
The cause is an overlap, not a shortage of staff: shifting the least critical task into its float is often enough.
3 · Recall
6. What is the baseline used for?
The baseline freezes the planned (dates, durations, work, costs): it is the comparison point that makes it possible to measure variances.
3 · Application
7. When should Meriem save the baseline?
The baseline is set on a finalised and validated schedule, before the start: too early it is unreliable, too late you lose tracking.
3 · Arbitration
8. A small adjustment occurs after the baseline. What does Meriem do?
The planned must not move: you do not overwrite the baseline at every adjustment; in the event of a major revision, you add one without overwriting the old one.
3 · Application
9. What does the Tracking Gantt compare?
The Tracking Gantt overlays real progress and the baseline: the variances (delay, overrun) become visible.
3 · Arbitration
10. For a costly task, which tracking does Meriem favour?
The actual work and the re-estimated remaining work are more precise than the subjective % complete and feed costs correctly.
3 · Recall
11. What does the 'Update Project' function do?
'Update Project' reschedules unfinished work after a given date — useful after a stoppage or a global delay.
3 · Application
12. A linked task runs late: what does Meriem do?
With linked tasks in automatic calculation, entering actuals is enough: Project realigns the successors and shows the impact on the finish date.
What's next?
Score ≥ 80%: move on to Level 4 — analysis, custom fields and visual reports with Meriem.
Score between 50% and 80%: go back over the section(s) you failed (3.1 critical path & float, 3.2 resource overallocation, 3.3 baseline, 3.4 progress tracking, 3.5 rescheduling), reread the lesson, then retake the test.
Score < 50%: reread the whole level 3 while applying each 48h challenge (critical path & float, relieving resources, baseline, progress meeting, rescheduling) before trying again.
And after that? Keep Meriem's reflexes — watch the critical path, use the float, freeze the baseline, track actuals and reschedule properly: level 4 connects them to analysis and reporting.