Level 3 exam — harder

Exam — fresh questions

3 · Recall

1. What is the critical path?

The critical path is the sequence of zero-float tasks that determines the finish date: any delay on it pushes back the project.
3 · Application

2. Meriem wants to absorb a small contingency without moving delivery. Where does she act?

You use the float of non-critical tasks: a delay absorbed in the float does not move the finish date.
3 · Arbitration

3. To shorten a project, what is the right approach?

Only the critical path moves the finish: crashing or fast-tracking, then you recheck that a new critical path does not appear.
3 · Recall

4. What does a resource overallocation correspond to?

An overallocation (overload) occurs when more than the available capacity is demanded: Project flags it in red.
3 · Application

5. Two tasks require the same site supervisor at the same time. What does Meriem do?

The cause is an overlap, not a shortage of staff: shifting the least critical task into its float is often enough.
3 · Recall

6. What is the baseline used for?

The baseline freezes the planned (dates, durations, work, costs): it is the comparison point that makes it possible to measure variances.
3 · Application

7. When should Meriem save the baseline?

The baseline is set on a finalised and validated schedule, before the start: too early it is unreliable, too late you lose tracking.
3 · Arbitration

8. A small adjustment occurs after the baseline. What does Meriem do?

The planned must not move: you do not overwrite the baseline at every adjustment; in the event of a major revision, you add one without overwriting the old one.
3 · Application

9. What does the Tracking Gantt compare?

The Tracking Gantt overlays real progress and the baseline: the variances (delay, overrun) become visible.
3 · Arbitration

10. For a costly task, which tracking does Meriem favour?

The actual work and the re-estimated remaining work are more precise than the subjective % complete and feed costs correctly.
3 · Recall

11. What does the 'Update Project' function do?

'Update Project' reschedules unfinished work after a given date — useful after a stoppage or a global delay.
3 · Application

12. A linked task runs late: what does Meriem do?

With linked tasks in automatic calculation, entering actuals is enough: Project realigns the successors and shows the impact on the finish date.