Level 2 exam — harder

Exam — fresh questions

2.1 · Recall

1. What is the WBS?

It describes the WHAT, not the WHEN; 100% rule.
2.1 · Application

2. Bilal breaks “site redesign” into one-week packages each with an owner. What does he check next?

Good breakdown covers all scope, adding nothing and forgetting nothing.
2.2 · Recall

3. What is the difference between effort and duration?

4 person-days by 2 people don't necessarily last 2 days (coordination, availability).
2.2 · Application

4. Why does Bilal estimate an uncertain package as optimistic / likely / pessimistic?

Three-point estimation objectifies the margin; communicate a range.
2.3 · Application

5. What does a bar represent in a Gantt chart?

The Gantt visualizes the schedule; sequencing = respecting dependencies.
2.3 · Arbitration

6. Bilal's Gantt shows everything in parallel from day 1, with no links. What to conclude?

A Gantt without dependencies is a wish list, not a schedule.
2.4 · Recall

7. What is the critical path?

A delay on a critical (float-free) task delays the whole project.
2.4 · Application

8. Bilal must save one week. Where must he act?

Speeding a non-critical task changes nothing to total duration.
2.5 · Application

9. What does Bilal's workload plan reveal?

Assigning resources reveals overloads, invisible on the raw Gantt.
2.5 · Arbitration

10. Bilal's developer is scheduled at 100% three weeks running. What decision?

At 100%, the slightest contingency derails; aim for a sustainable load (~80%).
2.6 · Application

11. What must Bilal's prudent budget include, beyond estimated cost?

Contingencies always occur; with no reserve, the first one derails.
2.6 · Arbitration

12. Mid-project, actual exceeds plan on one package. What does Bilal do?

A variance detected early is corrected; discovered at the end, it becomes a crisis.