Level 1 exam — harder

Exam — fresh questions

1.1 · Recall

1. What is the scoping note for?

It aligns stakeholders on the “why” and avoids the initial misunderstanding.
1.1 · Application

2. Bilal gets “we need software, sort it out”. His first reflex?

Clarify the problem before the solution, then get the note validated.
1.2 · Recall

3. What does the “T” of SMART mean?

Time-bound: every objective is bounded by a deadline.
1.2 · Application

4. Which of these objectives is SMART?

Precise, quantified, dated: we'll know whether it is met.
1.2 · Arbitration

5. The owner wants to add “modernize the image” to the objective, with no schedule or means change. What does Bilal do?

A stable objective is the course: any change = formal sponsor decision.
1.3 · Application

6. What must Bilal write to protect against scope creep?

The written boundary (included/excluded/assumptions), validated, is the bulwark.
1.3 · Application

7. A client asks for “a small addition, it takes 5 minutes”. Reflex?

Cumulated “small” additions explode schedule and budget.
1.3 · Arbitration

8. The “items file provided on the 15th” assumption fails. What to do?

An assumption is validated and monitored; if it falls, reassess.
1.4 · Application

9. The accountant (high power, low interest): which strategy?

High power + low interest = keep satisfied, without drowning in detail.
1.4 · Arbitration

10. An influential warehouse worker opposes the project in a meeting. What does Bilal do?

A heard opponent often becomes an ally — or a neutralized obstacle.
1.5 · Application

11. What must the owner sign to give the “go”?

Signed by the sponsor, the charter mandates the project manager.
1.5 · Arbitration

12. The vendor slips and Bilal can no longer arbitrate alone. Where does he escalate?

Steering decides and arbitrates; the project committee tracks operations.