12 questions to validate the fundamentals: project nature, lifecycle, golden triangle and approach choice.
Answer everything, then click Check: your score and explanations will appear.
0.1 · Recall
1. What characterizes a project (vs an ongoing operation)?
A project is a temporary effort for a unique outcome.
0.1 · Application
2. Must you be the domain's technical expert to lead a project?
Their key skills are methodological and human.
0.2 · Recall
3. What are a project's classic phases?
Milestones (duration-free) mark decisions between phases.
0.2 · Application
4. Bilal places “validated mockup” between scoping and delivery. What is it?
"Specifications validated", "acceptance pronounced" are milestones.
0.2 · Arbitration
5. Bilal wants to skip initiation to “save time”. What do you answer?
Upfront invested time pays back generously in execution.
0.3 · Recall
6. What does the golden triangle link?
These three constraints balance out; don't maximize everything.
0.3 · Application
7. Facing “faster, cheaper and more complete”, what does Bilal do?
Making constraints explicit protects the project.
0.3 · Arbitration
8. Budget is fixed and the date imposed, but the client adds features. What is the best lever?
Cutting quality creates debt paid later.
0.3 · Application
9. Why does Bilal list stakeholders from the scoping stage?
Their sometimes contradictory expectations weigh on trade-offs.
0.4 · Application
10. When to prefer an agile approach?
Predictive for stable needs, agile for uncertainty.
0.4 · Application
11. Frozen host migration vs fuzzy-need app: what does Bilal choose?
The choice is contextual; hybrid combines by phase.
0.4 · Arbitration
12. A colleague claims: “agile is better, and means no planning”. Your answer?
The right reflex: choose or combine by project; agile doesn't mean plan-free.
What's next?
Score ≥ 80%: move on to Level 1 — V3 (scoping, SMART objectives, scope, stakeholders, project charter).
Score < 80%: review the missed sections (0.1 project vs operation, 0.2 phases and milestones, 0.3 triangle and trade-offs, 0.4 predictive vs agile), reread the explanations above, then retake the test.