Level 0 exam — harder

Exam — fresh questions

0.1 · Recall

1. What characterizes a project (vs an ongoing operation)?

A project is a temporary effort for a unique outcome.
0.1 · Application

2. Must you be the domain's technical expert to lead a project?

Their key skills are methodological and human.
0.2 · Recall

3. What are a project's classic phases?

Milestones (duration-free) mark decisions between phases.
0.2 · Application

4. Bilal places “validated mockup” between scoping and delivery. What is it?

"Specifications validated", "acceptance pronounced" are milestones.
0.2 · Arbitration

5. Bilal wants to skip initiation to “save time”. What do you answer?

Upfront invested time pays back generously in execution.
0.3 · Recall

6. What does the golden triangle link?

These three constraints balance out; don't maximize everything.
0.3 · Application

7. Facing “faster, cheaper and more complete”, what does Bilal do?

Making constraints explicit protects the project.
0.3 · Arbitration

8. Budget is fixed and the date imposed, but the client adds features. What is the best lever?

Cutting quality creates debt paid later.
0.3 · Application

9. Why does Bilal list stakeholders from the scoping stage?

Their sometimes contradictory expectations weigh on trade-offs.
0.4 · Application

10. When to prefer an agile approach?

Predictive for stable needs, agile for uncertainty.
0.4 · Application

11. Frozen host migration vs fuzzy-need app: what does Bilal choose?

The choice is contextual; hybrid combines by phase.
0.4 · Arbitration

12. A colleague claims: “agile is better, and means no planning”. Your answer?

The right reflex: choose or combine by project; agile doesn't mean plan-free.
What's next?