Level 0 exam — harder

Exam — fresh questions

0.1 · Discrimination

1. Which distinction best sums up purchasing vs procurement?

Purchasing decides from whom and under what conditions to buy (medium/long term), procurement executes daily within that framework.
0.1 · Application

2. In a small company, one person wears all three hats. What is the most frequent mistake?

Operational urgency crushes purchasing work (benchmarking, renegotiating), yet the most profitable: you need protected dedicated time.
0.1 · Synthesis

3. What are the three flows the supply chain synchronises?

Physical (goods), information (orders, forecasts) and financial (invoices, payments) must align.
0.2 · Discrimination

4. What do upstream and downstream mean in a supply chain?

Upstream is supplier side, downstream customer side; physical goes downstream, money goes upstream.
0.2 · Application

5. A store sees +10% demand and orders +20% as a precaution. Which phenomenon does this amplification upstream illustrate?

Without information sharing, each link adds its safety margin and amplifies variation: that's the bullwhip effect.
0.2 · Choice

6. To reduce the bullwhip effect, which action is most effective?

Performance is collective: sharing information smooths shocks, withholding it worsens them.
0.3 · Discrimination

7. What does total cost of ownership (TCO) include?

TCO adds all delivered costs; it often reverses ranking based on price alone.
0.3 · Scenario

8. A critical part that stops production is offered cheaper with twice the lead time. What to do?

On a critical purchase, reliability prevails: the cost of a stoppage far exceeds a few percent saving.
0.3 · Synthesis

9. What is the fourth dimension completing the cost-quality-time triangle?

Risk (financial health, dependencies, location) has become central: a chain optimised only on costs is fragile.
0.4 · Application

10. In the purchasing cycle, which document contractually commits the order?

The PO formalises references, quantities, prices and lead times: it's the committing piece.
0.4 · Discrimination

11. What is lead time?

Lead time is end-to-end; it sizes stocks, not just supplier's announced time.
0.4 · Exclusion

12. Which is NOT a supplier reliability indicator?

SKU is the item identifier (reference); OTD, OTIF and service level measure reliability.
What's next?
Back to the guideGuide contents